Written by Sharaz Zaman, Founder of GM Professional Accountants, AAT Member with 15+ years London accounting experience.

Construction work in progress (WIP) is the value of labour, materials and overhead tied up in incomplete projects at your balance sheet date. Calculating it correctly ensures your profit and loss account reflects real performance, not cash timing, and keeps your accounts compliant with UK GAAP under FRS 102.

Definition

Work in progress accounting in construction is a method of recording the direct labour, materials, subcontractor costs and allocated overhead of partially completed contracts so that revenue and profit are recognised as work is performed rather than at project completion.

Key Takeaways

WIP sits on your balance sheet as a current asset and must be calculated at each reporting date.

The percentage-of-completion method links revenue to costs incurred, preventing artificial peaks and troughs in your P&L.

Underbilling creates a WIP asset; overbilling creates a liability. Both affect your balance sheet and must be reconciled.

Revised FRS 102, effective for periods beginning on or after 1 January 2026, introduces a new five-step revenue recognition model that changes how construction profits are timed.

GM Professional Accountants prepares WIP schedules and construction accounts for contractors across London and Essex, including clients in Ilford, Old Street and Wimbledon.

What Is Work in Progress in Construction Accounting?

In most businesses, revenue recognition is straightforward: deliver the work, raise the invoice, book the sale. Construction does not work that way. Projects run across months or years, and recording income only when cash arrives would make your management accounts meaningless at any point mid-contract.

Work in progress accounting solves this by matching revenue to the percentage of a contract that has been completed. The costs you have incurred to date, as a proportion of total estimated costs, tell you how much of the contract value you have earned. That earned-but-not-yet-invoiced amount sits on your balance sheet as a current asset until billing catches up.

For contractors in London and Essex, accurate WIP accounting is not merely best practice. Lenders, bonding companies and HMRC all expect your accounts to reflect economic reality, not cash timing. Misstated WIP leads to overstated profits, unexpected tax bills and failed covenant tests.

How Do You Calculate Construction WIP? A Step-by-Step Example

The core formula is simple. The complication is gathering accurate data for each active contract. Here is the standard approach:

Step 1: Establish total contract value

Include the original contract sum plus any approved variations. Pending variations should be tracked separately until formally approved.

Step 2: Calculate the percentage of completion

Percentage complete = Costs incurred to date divided by total estimated costs. If you have spent £60,000 on a project budgeted at £150,000, you are 40% complete.

Step 3: Calculate earned revenue

Earned revenue = Contract value multiplied by percentage complete. On a £200,000 contract that is 40% complete, earned revenue is £80,000.

Step 4: Compare to amounts billed

If you have only invoiced £60,000, you have an underbilling of £20,000. That underbilling is your WIP asset. If you had billed £90,000, the £10,000 excess would be an overbilling liability.

What Do the Journal Entries for Construction WIP Look Like?

Using the example above: contract value £200,000, total estimated costs £150,000, costs incurred to date £60,000, invoiced to date £60,000.

AccountDebitCreditNarrative
Cost of Sales£60,000Labour, materials and subcontractor costs incurred
Creditors / Bank£60,000Payments to suppliers and subcontractors
WIP Asset (Balance Sheet)£20,000Underbilling: earned £80,000, invoiced £60,000
Revenue (P&L)£20,000Revenue recognised on completion percentage not yet billed

For an overbilling scenario, the entry reverses: credit a Deferred Income or Overbilling liability account and debit revenue to reflect that you have collected cash ahead of the work performed.

What Is the Amounts Recoverable on Contracts Calculation?

Amounts Recoverable on Contracts (AMROC) is the balance sheet label that describes the WIP asset when it arises from long-term construction contracts. It appears as a current asset when you have earned more revenue than you have invoiced. The formula is:

(Total Contract Value x Percentage of Completion) minus Amounts Invoiced to Date

Using the worked example: (£200,000 x 40%) minus £60,000 = £20,000 AMROC balance. This £20,000 appears on your balance sheet under current assets and represents income that is legally yours but not yet invoiced.

AMROC must be reviewed at every reporting date. If your cost estimates change, the percentage complete changes, and so does the AMROC balance. Construction accountants at GM Professional Accountants review this position monthly for clients across London and Essex, ensuring the balance sheet accurately reflects contract progress at all times.

What Does a Construction WIP Schedule Look Like?

A WIP schedule brings together every active contract in a single document, updated at each month-end or reporting period. Here is an example format for a contractor with three live projects:

ProjectContract ValueEst. Total CostCost to Date% CompleteEarned RevenueInvoicedUnder / (Over) Billing
Office Fit-Out, EC2£200,000£150,000£60,00040%£80,000£60,000£20,000
Residential Extension, Ilford£85,000£65,000£52,00080%£68,000£75,000(£7,000)
Warehouse Refurb, Essex£320,000£240,000£96,00040%£128,000£128,000Nil
Total£605,000£208,000£276,000£263,000Net WIP: £13,000

Green figures indicate underbilling (WIP asset). Red figures in brackets indicate overbilling (deferred income liability).

What Is the Difference Between Underbilling and Overbilling in Construction?

FeatureUnderbillingOverbilling
What it meansEarned more than invoicedInvoiced more than earned
Balance sheet treatmentCurrent asset (AMROC or WIP)Current liability (Deferred Income)
Cash flow impactCash lag: work done, money not yet collectedCash lead: money collected, work still to do
Common causeSlow invoice cycles, milestone delaysDeposit-heavy contracts, early stage payments
Risk if mishandledUnderstated profit, missed tax obligationsInflated short-term profit, cash shortfall later
Journal entryDr WIP Asset / Cr RevenueDr Revenue / Cr Deferred Income

How Does FRS 102 Affect Construction WIP Revenue Recognition from 2026?

HMRC and Accounting Change Alert

The revised FRS 102 is effective for accounting periods beginning on or after 1 January 2026. If your company year-end is 31 March, the first affected accounts will be for the year ending 31 March 2027. Construction contracts are now assessed under the general five-step revenue recognition model rather than the previous sector-specific rules.

Under the old FRS 102 framework, construction revenue and costs were smoothed in line with percentage of completion, producing a consistent margin across the contract life. The revised standard keeps revenue recognition linked to progress, but costs are now recognised when actually incurred. This means project margins can appear uneven from period to period even where the overall contract profit remains unchanged.

The five-step model requires you to: identify the contract, identify each separate performance obligation, determine the transaction price, allocate that price to each obligation, and recognise revenue as each obligation is satisfied over time or at a point in time.

For most construction contracts, revenue will still be recognised over time because the customer controls the work in progress as it is created, or the contractor has an enforceable right to payment for work performed to date. However, you now need documented evidence of this for each contract individually.

For further detail on how FRS 102 changes interact with your construction accounts, see our guide: FRS 102 Lease Changes 2026: What They Mean for Construction Firms.

What Are the Most Common Construction WIP Accounting Mistakes?

1

Treating overbilling as profit

Cash collected ahead of work performed is a liability, not profit. Using it as profit can leave projects without funds to complete.

2

Not updating cost to complete estimates

If site conditions change, your percentage complete changes. Stale estimates produce inaccurate WIP and misleading management accounts.

3

Including unapproved variations in contract value

Pending variations inflate earned revenue and the AMROC balance. Only approved changes should enter the main WIP calculation.

4

Failing to link WIP to the profit and loss account

The WIP schedule must reconcile to both the P&L and the balance sheet. Any discrepancy signals a posting error or a missed contract.

5

Running WIP reports only at year end

Monthly WIP reviews catch cost overruns before they become crises. By year end, it is too late to change the outcome.

How Often Should You Run a WIP Report?

A WIP schedule should be produced at the end of every month, not just at year end. For high-value or fast-moving contracts, many contractors review WIP weekly to track expenses, billing and profitability in near real time.

Monthly WIP meetings between your finance team and site project managers are best practice. The accountant brings the numbers; the project manager brings the on-site reality. If there is a mismatch between what the spreadsheet says and what is happening on site, that gap needs reconciling before the next billing cycle.

Do Construction Companies in London Need an Audit or Specialist Accountant?

Whether you need an audit depends on your company size thresholds, though the rules around this are changing. Accurate WIP accounting is relevant whether you are audit-exempt or not, because it drives your statutory accounts, your corporation tax return and your management information.

If you are tendering for contracts, your WIP position can affect how lenders and clients assess your financial standing. See our related guides for more detail:

Does Your Construction Company Still Need an Audit? A 2026 Guide

Understand the size thresholds and exemptions under current UK company law.

How to Pass the Financial Standing Test in a Construction Tender

Your WIP schedule is often scrutinised during tender financial assessments.

Small Business Accountants for Construction Companies in London

Specialist support for London and Essex contractors from a dedicated construction accounting team.

Frequently Asked Questions About Construction WIP Accounting

Where does WIP sit on the balance sheet?

WIP sits under current assets when you have earned more revenue than you have invoiced. When you have invoiced more than you have earned, the excess sits under current liabilities as deferred income.

Is WIP a current asset or a fixed asset?

In construction accounting, WIP is a current asset. It represents amounts recoverable on contracts within the normal trading cycle, typically converted to cash within twelve months as projects complete and invoices are settled.

Does WIP affect corporation tax?

Yes. WIP adjustments change your reported profit for the period, which directly affects your corporation tax liability. Understating WIP understates profit and delays tax; overstating WIP accelerates tax. Accuracy matters both for compliance and for cash flow planning.

Do I need a WIP schedule if I use Xero or QuickBooks?

Accounting software does not automatically produce a construction WIP schedule. You still need to build or maintain a separate WIP schedule, usually in a spreadsheet linked to your job cost reports, and then post the resulting adjustment entries into your software. Some construction-specific add-ons (such as Procore or Buildertrend) can generate WIP data, but the reconciliation to your accounting records remains your responsibility.

How does Making Tax Digital affect construction WIP reporting?

Making Tax Digital for Income Tax (MTD for ITSA) is being rolled out from April 2026 for sole traders and landlords earning above the threshold. Limited companies will follow later. MTD requires digital record-keeping and quarterly updates, which means your WIP position needs to be reconciled quarterly rather than only at year end. Contractors using manual spreadsheets for WIP will need to review their processes now.

Need Help With Your Construction WIP Accounts?

GM Professional Accountants prepares monthly WIP schedules, management accounts and year-end statutory accounts for construction businesses across London and Essex. Our team works with contractors in Ilford, Old Street, Wimbledon and East London, as well as clients throughout Essex. Whether you need a first WIP schedule set up or an existing process reviewed against the new FRS 102 framework, we can help.

GM Professional Accountants serves clients across London and Essex and is regulated by the AAT.

Written by GM Professional Accountants Team
GM Professional Accountants is an AAT-regulated accounting practice serving construction businesses, contractors and tradespeople across London and Essex. Registered office: Ilford, Essex. This article is for general information only and does not constitute specific accounting or tax advice. For guidance tailored to your contracts and trading position, speak to a qualified adviser.

About the author

Written by the team at GM Professional Accountants, an AAT regulated London practice working with construction, property, healthcare and retail businesses. Meet the team.